Paving Updates – 10/9/2026
CO-OP PAVING PROJECT TO BEGIN WEDNESDAY, OCTOBER 14, 2026
The Town of Phillipsburg’s Co-Op Paving Project is scheduled to begin on Wednesday, October 14, 2026, starting with milling operations.
Wednesday, October 14 – Milling
- Claremont Street – Stanley Street to Bartlett Street
- Grand Street – Madison Street to Dead End
- Lock Street – Chestnut Street to South Main Street
- Lyndale Street – Logan Street to Dead End
- Pearl Street – Madison Street to Lyndale Street
Thursday, October 15 & Friday, October 16 – Milling
- Ann Street – Green Street to Sayre Street
- Mill Street – Steele Street to Kent Street
- Webster Street – Wilbur Avenue to Sayre Street
- Wilbur Avenue – James Street to Kent Street
No Parking signs have already been posted in preparation for the work; however, the No Parking restrictions will not be enforced until Wednesday, October 14. Please do not park in posted areas once the restrictions take effect so crews can complete the work safely and efficiently.
Paving will follow the milling work. We will provide residents with additional information regarding the paving schedule as soon as those dates are confirmed.
Thank you for your cooperation and patience as we continue improving our Town roadways!